This doc explains features in ClickUp 2.0. Looking for a 1.0 doc? Check out this link!

With this feature, when you change a parent task's due date, we'll ask you if you want us to automatically change its subtask due dates by the same amount.

For example, if you change a parent task due date from July 1 to => July 6, that's a change of  +5 days  so we'll also increase all subtask dates by 5 days. 

How to enable this feature:

  1. Go to ClickApps  
  2. Ensure the “Remap Subtask Due Dates” ClickApp is enabled

How to use this feature: 

  1. Change a parent task due date (that has subtasks with due dates)
  2. You'll get this prompt below, just click change subtask dates  